Showing posts with label Hydropower Plant. Show all posts
Showing posts with label Hydropower Plant. Show all posts

Tuesday, January 25, 2011

Power cuts expected for months to come

Vietnam is faced with occasional power shortages during the next two or three months – and the situation is not forecast to improve in the new year.

Statistics from State-run Electricity of Vietnam Group (EVN) show that in the first nine months of the year, total water in national reservoirs was 33.3 billion cubic metres less than at the same period last year.

This is sufficient to cause hydro-power shortages of up to 6 billion kWh.

Total electricity production from all sources last month amounted to just over 8.6 billion kWh, up 15 per cent on the same period last year.

Reduced water levels have left power authorities perplexed at the possibility of power shortages and cut-offs in the near future as well as shortages next year.

To deal with the issue, Prime Minister Nguyen Tan Dung has asked the EVN to regulate power supplies for production and consumption and to try and limit cutting supplies.

He said the sector should mobilise oil-fired and coal-fired power plants, bring newly-built plants into operation and promote the saving of power among the population.

Deputy general director of the EVN Dang Hoang An said hydro power normally produced more than 59 per cent of total needs.

He said while the sector might be able to meet demand for 25 billion kWh in the last three months of this year, an additional problem was the temporary closure of Ca Mau Gas Factory PA3 pipelines for maintenance.

Ta Van Luan, director of Yaly Hydropower Plant, said water levels at Pleikrong Reservoir were about 537m, compared to 570m for the same period last year.

He said he did not expect the situation to improve in the near future and that the plant had been operating only five hours a day, lower than full capacity.

A similar situation is being experienced at the largest Yaly Hydropower Plant, which has a water level of 490m, 25m lower than average level last year.

Luan said water flow into Yaly reservoir was 160cu.m a second, but its four turbines needed 420cu.m a second to reach full capacity.

He said in the first nine months of the year, the plant had run at half of its capacity because of the low water levels.

And that some water would be saved for next year. The plant is expected to supply 4 billion kWh this year, compared to its expected production of 5.5 billion kWh.

Reservoirs in the Central Highlands and the south are facing drought.

Le Van Quang, deputy director of Da Nhim-Ham Thuan-Da Mi Hydropower Company said the water level at Ham Thuan was only 39cm above the lowest level and supplied water for electricity for only eight hours a day.

He said the 400MW Tri An Hydropower Plant had received 4.1 billion cu.m, 2 million cu.m lower than at the same period last year. Its water level was less than a metre above the lowest level.

Director of Tri An Hydropower Plant Nguyen Kim Phuc said low water levels had reduced expected electricity production this year to 1-1.2 billion kWh, the lowest level in 23 years of operation.

 

Related Articles

Monday, January 24, 2011

Power cuts expected for months to come

HA NOI — Viet Nam is faced with occasional power shortages during the next two or three months – and the situation is not forecast to improve in the new year.

Statistics from State-run Electricity of Viet Nam Group (EVN) show that in the first nine months of the year, total water in national reservoirs was 33.3 billion cubic metres less than at the same period last year.

This is sufficient to cause hydro-power shortages of up to 6 billion kWh.

Total electricity production from all sources last month amounted to just over 8.6 billion kWh, up 15 per cent on the same period last year.

Reduced water levels have left power authorities perplexed at the possibility of power shortages and cut-offs in the near future as well as shortages next year.

To deal with the issue, Prime Minister Nguyen Tan Dung has asked the EVN to regulate power supplies for production and consumption and to try and limit cutting supplies.

He said the sector should mobilise oil-fired and coal-fired power plants, bring newly-built plants into operation and promote the saving of power among the population.

Deputy general director of the EVN Dang Hoang An said hydro power normally produced more than 59 per cent of total needs.

He said while the sector might be able to meet demand for 25 billion kWh in the last three months of this year, an additional problem was the temporary closure of Ca Mau Gas Factory PA3 pipelines for maintenance.

Ta Van Luan, director of Yaly Hydropower Plant, said water levels at Pleikrong Reservoir were about 537m, compared to 570m for the same period last year.

He said he did not expect the situation to improve in the near future and that the plant had been operating only five hours a day, lower than full capacity.

A similar situation is being experienced at the largest Yaly Hydropower Plant, which has a water level of 490m, 25m lower than average level last year.

Luan said water flow into Yaly reservoir was 160cu.m a second, but its four turbines needed 420cu.m a second to reach full capacity.

He said in the first nine months of the year, the plant had run at half of its capacity because of the low water levels.

And that some water would be saved for next year. The plant is expected to supply 4 billion kWh this year, compared to its expected production of 5.5 billion kWh.

Reservoirs in the Central Highlands and the south are facing drought.

Le Van Quang, deputy director of Da Nhim-Ham Thuan-Da Mi Hydropower Company said the water level at Ham Thuan was only 39cm above the lowest level and supplied water for electricity for only eight hours a day.

He said the 400MW Tri An Hydropower Plant had received 4.1 billion cu.m, 2 million cu.m lower than at the same period last year. Its water level was less than a metre above the lowest level.

Director of Tri An Hydropower Plant Nguyen Kim Phuc said low water levels had reduced expected electricity production this year to 1-1.2 billion kWh, the lowest level in 23 years of operation. ­— VNS

Related Articles

Tuesday, January 11, 2011

EVN pledges sufficient power supply in Q4

HCMC – The Electricity of Vietnam Group (EVN) pledged on Monday that the State utility would try its best to meet the country’s total power demand at some 25 billion kilowatt hours in the fourth quarter of this year.

The group’s deputy general director Dang Hoang An told an online meeting organized by the Ministry of Industry and Trade that EVN would mobilize more energy sources to minimize power outages.

EVN has had to purchase a maximum volume of power from other sources including 67.8 billion kilowatt hours from China to lessen impacts of the power supply crunch in the January-September period, An told the meeting to review industrial production in the first three quarters. He explained that power supply was strain lately due to droughts, causing the water flow to reservoirs to dwindle.

According to a report issued on Monday by the Ministry of Industry and Trade, in the last quarter of the year, some power plants are expected to start commissioning such as the first power turbine of Son La Hydropower Plant, and the first turbines of Song Tranh 2 Hydropower Plant and Dong Nai 3 Hydropower Plant.

The forthcoming operation of such hydropower plants will help ease the power shortage in the country.

However, An noted that the power outages could still occur for around ten days this month as PetroVietnam has just announced a scheme to maintain the gas pipelines of Ca Mau Gas Power Complex over ten days.  

Furthermore, An of EVN also told the ministerial meeting that the most worrying problem for EVN is to cope with the water storage in the coming months, particularly during the dry season in the first half of next year.

“EVN will work with the Ministry of Agriculture and Rural Development in the coming days to seek measures for this matter,” An said, referring to the conflict of storing water for power generation and pumping water for farming.

Speaking at the meeting, Minister of Industry and Trade Vu Huy Hoang asked PetroVietnam to work with its Malaysian partner to speed up the gas pipeline maintenance and for the time being use oil to fuel the Ca Mau power plant so that it can run at full capacity in the pipeline maintenance process.

Related to industrial production of the country, the ministry in its report expected a growth rate of 14% as targeted for the manufacturing sector this year, after attaining an industrial production value of VND574 trillion in the year to date, a year-on-year increase of 13.8%.

The ministry also predicted that for the whole year 2010, the country will also obtain total export revenue of US$69 billion, an increase of 21%, while import expenditure is estimated at US$82 billion, up 17% year-on-year.

Related Articles

Tuesday, November 9, 2010

Power projects hit by drought

power-grid

Many small and medium hydropower plants in the Central Highlands do not have enough water to operate efficiently although the rainy season is about to end.

Most hydroelectric companies in Dak Lak complain production has reached only about half of their targets because of the drought-like weather conditions.

Some small plants had to shut down temporarily to accumulate enough water, they said.

There are four hydropower plants on the Serepok River - the Buon Tu Srah Hydropower Plant with a 520 million cubic metres reservoir in Lak District; the Buon Kuop Hydropower Plant in Dak Lak Province's Krong No District; Dray H'Linh, Serepok 3 Plants in Dak Nong Province's Cu Dut District and Serepok 4 in Buon Don District, Dak Lak.

Tran Van Khanh, director of the Buon Kuop Hydropower Company which operates the Buon Tu Srah and Serepok 3 plants, said the extended drought resulted in record low water levels in the Serepok River. He said the Buon Tu Srah Dam, whose reservoir can hold 520 million cu.m of water, had just around 60 million cu.m water.

This was the lowest since the plant was inaugurated in September 2009. Inadequate water in the Buon Tu Srah Reservoir has caused downstream hydropower plants to operate perfunctorily because upstream reservoirs have to accumulate water, he said.

Khanh said the State had assigned his company to provide 1.28 billion kWh of power this year, but it has only been able to produce 480 million kWh, about 38 percent of the year's plan.

"Compared with the same time last year, this is a record low water level. The rainy season in the Central Highlands often ends in November, but there is not enough water to operate the plants even now. With this situation, I am afraid the company will not reach 50 percent of the target," Khanh said.

An official who works at the Buon Tu Srah Reservoir said last Friday that the dam could not accumulate enough water and the plant had to stay idle at daytime.

The Krong No River in Dak Nong Province is no longer fierce and deep as it used to be, and a drop of several dozen meters in water levels in the dam is clearly visible.

Ho Van Bay, deputy secretary of Duc Xuyen Commune's People's Committee, said water levels in streams that linked to the Krong No River were so low that people could walk to the other side.

Nguyen Van Than, director of the Dak Lak Electricity Company, predicted that the situation would worsen in the coming months.

Water levels at the Ialy Hydropower Plant on the Se San River in Gia Lai and Kon Tum Provinces have also been reported at critically low levels and output capacity of the dam is said to be at 50 percent.

Ta Van Luan, director of Ialy Hydropower Company, said the company's production in the first eight months of this year has reached 50 percent of that assigned by the Vietnam Electricity Corporation.

Related Articles

Saturday, November 6, 2010

Power projects hit by drought

DAK LAK — Many small and medium hydropower plants in the Central Highlands do not have enough water to operate efficiently although the rainy season is about to end.

Most hydroelectric companies in Dak Lak complain production has reached only about half of their targets because of the drought-like weather conditions.

Some small plants had to shut down temporarily to accumulate enough water, they said.

There are four hydropower plants on the Serepok River - the Buon Tu Srah Hydropower Plant with a 520 million cubic metres reservoir in Lak District; the Buon Kuop Hydropower Plant in Dak Lak Province's Krong No District; Dray H'Linh, Serepok 3 Plants in Dak Nong Province's Cu Dut District and Serepok 4 in Buon Don District, Dak Lak.

Tran Van Khanh, director of the Buon Kuop Hydropower Company which operates the Buon Tu Srah and Serepok 3 plants, said the extended drought resulted in record low water levels in the Serepok River. He said the Buon Tu Srah Dam, whose reservoir can hold 520 million cu.m of water, had just around 60 million cu.m water.

This was the lowest since the plant was inaugurated in September 2009. Inadequate water in the Buon Tu Srah Reservoir has caused downstream hydropower plants to operate perfunctorily because upstream reservoirs have to accumulate water, he said.

Khanh said the State had assigned his company to provide 1.28 billion kWh of power this year, but it has only been able to produce 480 million kWh, about 38 per cent of the year's plan.

"Compared with the same time last year, this is a record low water level. The rainy season in the Central Highlands often ends in November, but there is not enough water to operate the plants even now. With this situation, I am afraid the company will not reach 50 per cent of the target," Khanh said.

An official who works at the Buon Tu Srah Reservoir said last Friday that the dam could not accumulate enough water and the plant had to stay idle at daytime.

The Krong No River in Dak Nong Province is no longer fierce and deep as it used to be, and a drop of several dozen meters in water levels in the dam is clearly visible.

Ho Van Bay, deputy secretary of Duc Xuyen Commune's People's Committee, said water levels in streams that linked to the Krong No River were so low that people could walk to the other side.

Nguyen Van Than, director of the Dak Lak Electricity Company, predicted that the situation would worsen in the coming months.

Water levels at the Ialy Hydropower Plant on the Se San River in Gia Lai and Kon Tum Provinces have also been reported at critically low levels and output capacity of the dam is said to be at 50 per cent.

Ta Van Luan, director of Ialy Hydropower Company, said the company's production in the first eight months of this year has reached 50 per cent of that assigned by the Viet Nam Electricity Corporation. — VNS